Project Youth Club

Nice day for a start!
Hallam Scaffold have provided edge protection
Rear elevation
Chippings on top roof
Multiple patch repairs
Bit grim looking
Lower level roof with felted over rooflights
Lower level again
These coverings will be stripped off and a felt vapour barrier installed.
Insulation is laid onto new vapour barrier
Timber curb is fixed at open end of insulation, note green mineral on underside of perforated venting felt
Perforated venting felt laid loose over insulation
Polyester underlay is laid over venting layer, giving partial bond to insulation.
Sequence of installation of a typical warm deck roof.
Hot bitumen bonds the layers together, this method is called pour and roll.
Ready to receive mineral surfaced cap sheet
Didn't always rain.
Elastomeric mineral surfaced cap sheet finish.
Detail at the gutter
Overview
Ready for fixing upstands
Looking down onto nearly completed lower roof. Where are the old rooflights?
Few edge details to complete.