Mastic Asphalt Roof Vents

Home

The roof deck had obviously failed due to lack of ventilation in roof void and with humid conditions within the building
With the old coverings and deck removed this is what greeted us
All defective timbers were cut out and replaced
Working area was limited
Another view
Tanalised laths are installed to allow ventilation of roof void
18mm exterior grade plywood is installed as the new deck
A lot of cooler units had to be temporarily moved to enable re-roofing works to be carried out

Forming the second coat of the internal angle fillet

1.

2.
3.
Curb detail
Curb and skirting detail
Breather vents have been installed to allow ventilation of roof void
Cooler units re-installed
Space was limited